Completed water service replacements along
Longvalley Road between Country Lane and North Branch Road
·
Completed connections between the existing water
main and the new water main at North Branch Road and Country Lane
·
Began storm sewer installation along Longvalley
Road from river working west.
·
Nicor has demobilized and will continue Phase II
of the gas main and service replacement along Longvalley Road once the storm
sewer work is completed.
Work Anticipated to be completed This week, August 29th
to September 2nd
·
Continue with storm sewer installation along
Longvalley Road
·
General Site clean-up prior to Labor Day
Weekend.
The contractor has started the final phase of the
underground utility improvements along Longvalley Road, storm sewer
installation. The contractor is replacing the existing storm sewer piping with
larger piping to the outfall at the river. Due to the size and location of the
new storm sewer, travelling along Longvalley Road has become increasingly more
difficult. The Village and contractor are committed to doing everything
possible to minimize these delays, but your patience and understanding is
definitely appreciated. Depending on work progress and weather conditions, the
storm sewer main line installation are anticipated to take another 2 to 3 weeks
to complete.